Project Background/Description
The adopted Formula 2040: The Master Plan for Parks, Recreation, and Open Space divides the county into nine Service Areas. From the center of each service area, recreational facility access should be within a 15-minute travel time. It was recommended that 12,000 sq ft of additional non-aquatic recreation space be constructed in the North College Park area. The Department has completed a feasibility study to determine the location, program, conceptual design, and cost for that facility. The final document can be viewed below. The study recommended two potential sites for a 13,000 sq ft community center, the Hollywood Shopping Center and Hollywood Park.
Status/Project Updates
Last Updated February 2023
This project is complete. The Department has requested funding for this project in the proposed FY24 CIP.
A summary of completed and anticipated project milestones is as follows:
Spring 2022 – Data Gathering and Community Outreach
Summer 2022 – Conceptual Design and Cost Estimates
Fall 2022 – Budget Request
Winter 2022 – Final Study Completed
Actual dates for the completion of the milestones are subject to change.