Cherryvale Park Playground Replacement

Project Background/Description

The Department of Parks and Recreation is replacing the playground equipment at Cherryvale Park. The playground replacement involves the removal and disposal of the existing equipment and the installation of new play equipment and engineered-wood-fiber surfacing.

The original playground provided equipment was beyond its useful life. The updated playspace will have equipment for children ages 2-5 and 5-12. Play elements and features will allow for climbing, spinning, swinging, playing instruments, sliding, and more!

Status/Project Schedule

Currently, the project is in the Procurement phase. A summary of anticipated milestones is as follows:

  • Summer 2021 – Construction Start
  • Fall 2021 – Construction Completion

Actual dates for the completion of the milestones are subject to change.

Project Contact

Jordan Exantus, AICP, LEED AP
Lead Park Planner (Northern Area)
Jordan.Exantus@pgparks.com
(301) 699-2541